PALOS VERDES ESTATES, Los Angeles County — The City of Palos Verdes Estates identified three road segments for storm-drain and pavement improvements under its FY2025–26 Annual Miscellaneous Infrastructure Project.
Official plans called for replacement of a 36-inch storm drain pipe on Via Cataluna, with a new manhole and junction structure; replacement of a 12-inch pipe and catch-basin reconstruction on Via Coronel; and concrete repair and grout injection to address a pavement void on Via Las Vegas.
What the published schedule does — and doesn’t — establish
The city awarded a construction contract to Mike Bubalo Construction and anticipated work from June into late July 2026. A notice scheduled daytime closures of Via Cataluna between Via Fernandez and Via Margarita during part of that period.
Those published closure dates have now passed. This retrospective article does not mean the road is closed today or that the project finished exactly on its anticipated date. Residents seeking final completion records or information on any remaining deficiencies can contact the city’s Public Works Department at engineering@pvestates.org.
Source: Palos Verdes Estates — FY25/26 Infrastructure Project Notice.
Support Palos Verdes Estates News
Choose how to support Palos Verdes Estates News:
Credit / Debit Card via StripeChoose your contribution amount on the secure California58 Stripe checkout. One-time support for independent local journalism.
Continue with PayPal Continue with ZelleZelle payments go to Vitaly Ataev Troshin. Please verify the recipient in your bank before sending. Availability depends on your bank.
Optional reader support. When possible, add “Palos Verdes Estates News” to the payment note. Contributions are not advertised as tax-deductible. Support does not influence editorial decisions.More from Palos Verdes Estates News
- Palos Verdes Estates Council: Three Candidates Lead for Three Open Seats →
- Palos Verdes Library District three library-board trustee seats: Beth K. Whittenbury, Jonathan Beutler, Maria D. Villa Lathrop Lead →
- Palos Verdes Estates Measure PVE: Yes Just Above Two-Thirds Tax Threshold →
- Lunada Bay Streets Received Slurry Seal in City’s August 2026 Roadwork Plan →
- Palos Verdes Estates Council Considered ADU Rule Changes to Align With California Law →
COMMUNITY
Comments
Join the California58 conversation. You must be signed in to comment.
Create a free California58 account or sign in with an available social provider.